North Carolina General Statute 87-1 establishes the mandatory licensing requirements for general contractors. According to this statute, any construction project that costs $40,000 or more requires the contractor to hold a valid general contractor’s license. This rule is important to keep standards high in the industry and to protect customers.
In many cases, projects can exceed initial estimates due to various factors. For instance, if a contractor quotes a job at $33,000, they might face additional requests from the client for extra work. Alternatively, increases in material costs can unexpectedly push the total over the $40,000 mark. When this occurs, the implications can be severe for an unlicensed contractor.
- Change Orders: If a client requests additional work, the total cost could easily surpass $40,000. In such cases, the contractor is essentially entering into a new contract that requires licensing.
- Material Cost Increases: Fluctuations in the market can lead to unexpected price hikes in materials. If these increases push the project cost beyond the threshold, the contractor’s lack of a license becomes a significant issue.
- Clear Contracts: Ensure that contracts include clauses that specify labor and material costs. Phrases like “labor and materials shall not exceed X amount” can provide clarity and protection.
- Anticipate Changes: Be aware of the possibility of change orders and build contingencies into your pricing. This can help accommodate potential increases in costs without breaching licensing laws.
- Stay Informed: Keep abreast of market trends affecting material costs and labor rates. Being proactive can help you make more accurate quotes.